RopeFactor Reference Open the calculator

Elevator rope order length: the four reeving formulas

RopeFactor estimates the required length of each hoist rope from travel, overhead, pit depth, machine location and roping ratio. Installation allowances are added to the calculated base length before the total is rounded up to the ordering increment.

Required dimensions

An elevation of a 1:1 overhead job showing the three dimensions the order-length formulas use: the rise from the bottom landing to the top landing, the overhead from the top landing up to the centreline of the drive sheave, and the pit depth from the bottom landing down to the pit floor. CAR OH RISE PIT top landing bottom landing pit floor
1:1 overhead arrangement. Overhead is measured to the drive sheave centreline and appears twice in the base-length formula.

Base length per hoist rope

The base rope length depends on machine location and roping ratio. The formulas below give the length of one hoist rope before installation allowances are added.

Base length per rope, before allowances
MachineRopingBase length
Overhead1:1Rise + Pit + 2·OH
Overhead2:12·Rise + 2·Pit + 4·OH
Basement1:13·Rise + 2·Pit + 4·OH
Basement2:1 (underslung)4·Rise + 2·Pit + 6·OH

On a basement 2:1 arrangement, overhead appears six times in the base-length formula. The overhead dimension should therefore be taken to the drive sheave centreline rather than using architectural overhead.

Allowances

Allowances cover hitch make-up, shortening during installation, and the second wrap on a double-wrap drive. They are added to the base length, and only then is the total rounded up to the stock increment — 10 ft, or 5 m.

Typical allowances
AllowanceImperialMetricApplies to
Hoist extra25 ft7.6 mevery hoist rope
Double wrap20 ft6.1 mevery hoist rope, when the drive is double-wrapped — including at 1:1
Governor20 ft6.1 mthe governor rope run
Compensation50 ft15.2 meach compensation rope or chain

The allowances above are planning values used for hitching, installation adjustment and double-wrap arrangements. They are not code requirements. Confirm final ordering allowances with the rope supplier and installation team before placing the rope order.

Governor and compensation runs

The governor rope forms a loop over the full rise, so both the rise and the pit appear twice:

Worked example

Machine
Overhead, 1:1, single wrap
Rise
200 ft
Overhead
8 ft
Pit depth
8 ft
Hoist ropes
6

Base = Rise + Pit + 2·OH = 200 + 8 + 16 = 224 ft

+ hoist extra 25 ft = 249 ft

ROUNDUP(249 ÷ 10) × 10 = 250 ft per rope

Governor = ROUNDUP((400 + 16 + 16 + 20) ÷ 10) × 10 = ROUNDUP(452 ÷ 10) × 10 = 460 ft

Order: 6 × 250 ft = 1,500 ft of hoist rope, plus 460 ft of governor rope.

The same job with the machine in the basement at 2:1 gives a base of 4·200 + 2·8 + 6·8 = 864 ft, which becomes 890 ft per rope after the allowance and rounding — 5,340 ft in total against 1,500 ft. The example shows the difference in rope quantity between an overhead 1:1 and a basement 2:1 arrangement.

This is a planning estimate. The rope-length calculation is intended for planning and order review. Final rope lengths should be checked against the approved elevator layout and the actual machine, sheave and hitch locations before material is ordered.

Run this on your own job

See also

ISO 8100-2 minimum rope safety factor ASME A17.1 minimum rope safety factor by speed A worked calculation example — full ISO and ASME reports Elevator overhead: which dimension is used?